SCADA/DCS supervisory system expansion
PORR S.A. hereby certifies that ZW Automation Sp. z o.o. participated, as our subcontractor, in the execution of the investment project entitled:
“Expansion of the Onshore Part of the LNG Regasification Terminal in Świnoujście” carried out for the Gas Transmission Operator GAZ-SYSTEM S.A. in the years 2023–2025.
The scope of works included:
Comprehensive and complete expansion of the Electrical Supervisory and Control System (ESCS):
- expansion of the existing telecommunication network infrastructure,
- prefabrication of communication and control cabinets,
- execution of FAT and SAT tests,
- addition of new data concentrators in the form of PLC controllers,
- modification of existing PLC controllers, server and operator stations within the PCS 7 system,
- works with the PCS 7 Power Control library and communication with field controllers (IED) in the IEC 61850 standard,
- data exchange integration using various communication protocols between devices and the existing Distributed Control System (DCS),
- ensuring reliable communication between individual subsystems forming the electrical network,
- ensuring system reliability on both software and hardware levels.
Comprehensive and complete expansion of the Integrated Fire Safety Management System (IFSMS) and the Fire and Gas Detection System (F&G):
- prefabrication of communication and control cabinets,
- execution of FAT and SAT tests,
- system connection,
- expansion of the fire and gas detection infrastructure,
- addition of new PLC controllers,
- migration of the existing F&G system to new server stations,
- modification of existing PLC controllers, server and operator stations within the PCS 7 system,
- commissioning of the Siemens SAFETY matrix,
- integration with the existing Distributed Control System (DCS),
- ensuring system reliability on both software and hardware levels.
All works were carried out in a professional manner, and the engineers of ZW Automation Sp. z o.o. demonstrated the required competencies and due diligence during the execution of their tasks.